Design-Build or not? Good Question
Sep 9, 2003 12:00 PM, Roger B. Hutchins, CPP
Whether one is an experienced security services buyer or a novice,
it is a good idea to consider all the options. And fundamental to the
choices is what kind of contracting method would be best suited for a
particular project.
Standard procurement models in both the private and government sectors
are based on one of the following:
-
developer build-to-suit
-
design-bid-build
-
design-build.
This article will examine how contracting methods work and why one
might be better in a particular instance than another.
Developer Build-to-Suit
When purchasing security-related products or services, the developer
build-to-suit usually doesn’t apply, although it might be
relevant to a purchase involving general construction, such as a new
visitor center building or vehicle inspection station.
Overall, engaging a developer to furnish a complete building project
has become more popular with government buyers in recent years.
Benefits include less risk for the buyer, reduced project management
requirements and deferred financial obligation. The delivery process is
entirely under the developer’s control. There can be variations
in the developer’s responsibilities — they may include all
the elements of a traditional design-bid-build arrangement or the
developer may act in a lesser capacity to provide what is essentially a
project management resource on behalf of the customer. One difficulty
with government procurement under a developer-based model is the
requirement for competitive procurement. This issue is often addressed
contractually between the owner and the developer and is more important
to the government buyer than the private sector buyer due to Federal
Acquisition Regulations (FARs).
Design-Bid-Build
This traditional delivery method is still the most widely used and best
understood contracting model. Compared to the developer-based or
design-build approach, it offers the buyer more control — but
does so at the expense of buyer resources that must be devoted to
manage the process. Here again there are ways to fine-tune the process
depending on the sophistication of the buyer’s resources. The
buyer might elect to perform the design work in-house or to hire a
construction manager to take control of the project after it has been
awarded. The size and type of a project may make this traditional model
more or less attractive.
Design-Build
The design-build model has become more popular in the government sector
due in part to the “less government” initiatives of recent
administrations and the popular “better, faster, cheaper”
mantra initiated by NASA and emulated by many others in government. For
commodity-type delivery orders, such as basic office buildings or
off-the-shelf systems, it has proven to be effective. There are
advantages for the buyer in the transfer of risk to the design-builder
and reduced project management resource requirements. But there are
also some downside issues if, for example, the project is complicated
or has unique characteristics that are hard to translate to the
design-builder’s scope of services.
So, how does the government buyer determine which method is best? And
how does the buyer protect and support his or her organization most
effectively? The answers lie in understanding and analyzing the
criteria.
Look Inside First
Although the government has long-established rules and regulations that
guide the buyer in the procurement cycle, it is not always as simple as
checking the right box on a GSA standard form. Anyone who has worked
with many different agencies knows that no two are organized the same
way. Nor do they possess the same depth and range of internal
resources. So first, the buyer should consider his internal
capabilities, including the following:
-
Does the buyer’s organization have internal design, construction management, and project management resources that are up to the challenge of the work being considered?
-
Has the project been well-defined in advance? Can the project’s needs be defined sufficiently to convey those needs to a systems contractor or builder?
-
Has the buyer completed a similar project? Was it a success or was the process not up to the challenge?
-
Does the particular organization have set-aside requirements that must be met? For example, are there Disadvantaged Business Enterprise (DBE) participation requirements? What kind of contract vehicles does the organization have in place that might satisfy the project’s requirements?
For security-related procurements, a given project can be complex
and involve work that interfaces or integrates with existing systems.
For example, consider the government agency that recently needed to
enhance its visitor access control program and improve its
facilities’ resistance to vehicle penetration. The project
involved a new building to house the visitor screening and registration
operation and new vehicle barriers. Part of the design involved
relocation of a legacy visitor management system, expansion of the
existing access control and CCTV systems and the installation of new
vehicle barriers that would be integrated into the design. In this
particular case, the access control and CCTV systems were being
serviced under existing maintenance agreements from two different
vendors. Modification of the existing systems or additions to those
systems as part of the work being considered would likely put the
existing maintenance agreements in jeopardy.
In this example, the client decided to break up the project to avoid
any conflicts with the existing agreements. The visitor center building
and related infrastructure work were awarded on a design-build basis to
a general contractor. Separate contracts for the system’s
installation work were awarded to the two existing vendors under
existing contracts. The systems design was performed in-house by
resident technicians and converted to bid documents by an outside
security consulting and engineering firm.
Contract specialists within the government are always looking for ways
to satisfy minority or disadvantaged business participation
requirements. Security-related procurements are not exempt. Thus, the
type of contracting vehicle and the performance method are often
reviewed by the Contracting Officer and the Contract Officer’s
Technical Representative to determine if DBE participation goals can be
met within the planned procurement. It has been demonstrated that DBE
participation goals can be achieved under a design-bid-build or
design-build approach.
The key is understanding the design requirements to determine if a
design-builder’s proposed team has the design expertise needed.
It is possible to direct a DBE design-builder to augment its team with
an appropriate design and engineering resource under a master
design-build contract. In a traditional design-bid-build approach, the
buyer has the freedom of selecting the design resources needed for a
particular project so this is not as important an issue to
consider.
Design Requirements
The second most critical question relates to the complexity of design.
The buyer may know in general terms what is required but not
necessarily at a detailed level. Contractually, the difference between
a design-bid-build and design-build may not seem significant. However,
design capabilities within a team vary greatly and may not be
adequately addressed under a design-builder’s typical team. For
this reason, the buyer should understand what level of design expertise
is required for a particular engagement and, if necessary, seek outside
assistance to define the requirements before soliciting
proposals.
Here is an example of design requirements gone bad. It involves a
government client who tried to procure a new access control system for
a large facility. On first examination, the buyer thought there was
sufficient information from the end-user to write a design-build RFP
for the procurement. However, the proposals submitted by the competing
design-builders were extremely far apart on price and technical
capability. Further, the end-user expected the design-builder to sort
out all the technical issues after the contract is awarded.
Unfortunately, the contract was awarded on the basis of the lowest bid,
and that offer assumed minimal design effort on the part of the
contractor. Only weeks after the award, the contractor claimed that the
design effort exceeded their scope of work and sought additional
compensation for those services. Consultants were brought into the
process when this impasse was reached, and they discovered that neither
party was “lily white” in the dispute. An examination
revealed that the RFP documents did not contain enough technical detail
and, far worse, provided almost no detailed performance requirements
relative to the design portion of the services.
Likewise, the contractor provided mountains of technical information
but didn’t explain how they would deliver a complete design. In
the end, the buyer chose to negotiate an increase in design scope to
fill the missing requirements.
Also from the viewpoint of complexity, the design component of a
project may be better served by an independent designer who has no
vested interest in selling products or equipment. Here’s why: As
the design becomes increasingly complicated, it becomes easier for the
design-builder to justify more goods and services than may be
necessary. One should not immediately conclude that the
design-builder’s actions are malicious. In some cases it is
simply a matter of familiarity with a particular product line that
leads a contractor to over-specify or over-supply a certain product. In
other cases, it is technical expertise that is lacking. In any event,
knowing the degree of technical complexity will allow the government
buyer to make an informed decision regarding how much technical design
expertise is needed and how to structure the contract.
Schedule
It seems that every project these days is on a fast-track schedule. And
with the spotlight focused on security, it is common for security
projects to be accelerated. Depending on how a project is managed,
there is no real time advantage for design-bid-build or design-build.
It’s really a question of project management.
In a design-build environment the schedule is less dependent on the
buyer’s project management team than it is on a design-bid-build.
It’s the approvals process that usually impacts the schedule
under either approach. Provided the design issues have been identified
in advance, either kind of project can be accelerated.
Want to use this article? Click here for options!
© 2008 Penton Media Inc.
Today's New Product
VideoIQ Day/Night Network CameraThe ultra wide dynamic range iCVR day/night network camera from VideoIQ features H.264 dual-streaming compression, content aware storage, intelligent networking, analytic detection and object search built into the unit. The camera features full D1 output at 30 frames-per-second and is tri-powered for Power-over-Ethernet (PoE), 24vAC and 12vDC, making it suitable for indoor and outdoor applications. The camera can store up to 160 GB of video and is network-friendly, requiring bandwidth only during critical events. |
advertisement
This month in Access Control
- Opening Up About Door Closers
- An Enterprise Approach
- The Framework For Open Systems
- On A Higher Plane
- More from April's issue
advertisement